Dear PVPUSD Community,
   
The start of a new school year always brings excitement and fresh opportunities for learning. While students and staff enjoyed a well-deserved summer break, our district continued important planning and implementation work for Measure SOS.
 
We are excited to share a few highlights of what has been accomplished recently, including: 
  • Selecting architecture and construction management firms for Measure SOS projects
  • Establishing a draft timeline and priority list for Measure SOS projects
  • Approving the first major Measure SOS project: the Miraleste Intermediate Pool
  • Scheduling groundbreaking for the Miraleste Intermediate Pool project
  
Miraleste Intermediate Swimming Pool Renovation 
The PVPUSD Board of Education officially approved the Miraleste Intermediate Swimming Pool Renovation project during its August 27, 2025 regular meeting, following a thorough pre-qualification and bidding process to ensure the work meets the highest standards of quality and accountability. 
  
Groundbreaking on the pool renovation project is scheduled for Sunday, September 14, at 10:00 a.m. at Miraleste Intermediate School. Members of the public are invited to attend. 
   
We anticipate that the pool will be completed and ready for use by March 2026. 
Miraleste Intermediate School: Pool GroundbreakingArchitecture and Construction Management Firm Selection 
Over the summer, PVPUSD conducted an extensive search for architects and management partners to assist with Measure SOS projects. The selection process included interviews, presentations, and strategic proposals from several firms. The board ultimately selected Balfour Beatty as the construction management firm, along with four architectural partners for Phase 1 Measure SOS projects: Ruhnau Clarke Architecture, tBP Architecture, DLR Group, and PBWS Architecture.
  
For more detailed information and ongoing updates about Measure SOS projects, we encourage you to join our Measure SOS Community Group and visit our Measure SOS webpage.
 
Draft Project Prioritization List 
In case you missed it, the PVPUSD Board of Education approved the draft construction schedule for Measure SOS Phase One projects during its meeting on June 3, 2025. 
 
With more than $135 million in projects approved, this first phase is just the beginning. Some work will be finished in this phase, while other projects will take more time and continue into later phases.
 
As work on Measure SOS projects continues, we look forward to sharing regular updates with you. Thank you for your continued partnership and investment in our schools.
 